(Optional) Plan Land Access for Sampling Events

<< Click to Display Table of Contents >>

EQuIS 6.6 Training Exercises  >>  EQuIS Sample Planning Module >

(Optional) Plan Land Access for Sampling Events

Overview

At some sites or locations, permission may be required to perform sampling or other field events. Similar to planning and scheduling for a sample, use the Land Access module in SPM to plan and schedule permission to enter a specific facility or visit a specific location.

 

Land access requirements may be defined for a location at the facility, planned task, and/or scheduled task levels as follows:

Land access requirements at the facility-level will apply to a location in ALL planned and scheduled tasks unless specifically overridden.

Planned task-level land access requirements will apply to a location in ALL scheduled tasks resulting from the planned task unless specifically overridden.

Scheduled task-level land access requirements should be updated to reflect the current status of access for individual scheduled events.

 

Exercise Scenario

We have received a Long-term Monitoring and Assessment Plan for the San Juan River in Utah, and we are required to conduct regular field sampling for the Gold King Mine facility. We are using an in-house field crew to collect the samples and perform field activities, and we have contracted a specific laboratory to perform analysis of the samples.

We need to specify the land access information in EQuIS SPM to ensure that the planned sampling events will occur without issues.

 

Goal

Exercise Objectives

Add Land Access Information for Planned Tasks

Update Land Access for a Scheduled Task

Generate Land Access Reports

 

Skills, Software and Permissions Required

EQuIS Sample Planning Module v6.6 must be installed on the Workstation

.NET Framework 4.0 or higher must be installed on the Workstation

Read/write permissions to the desired facilities

Access to the Premier Data or Premier Data & Graphics EQuIS Libraries

 

 

Goal

Objective: Add Land Access Information for Planned Tasks

1.Launch SPM and login to the desired facility.

For this exercise, login to the Gold King Mine Facility.

2.Select Open Plan and open the desired plan.

For this exercise, open the SJ River Monit <your initials> Plan.

3.Highlight an already defined Planned Task and select Edit spm-edit-task-button from the Planned Tasks group of the Plan ribbon on the main EQuIS SPM window.

For this exercise, highlight the Task1.SWQM.M_<your initials> Planned Task.

4.Select the Land Access tab.

5.Select Add spm-add-button to open the New Land Access Entry window.

6.Select the SYS_LOC_CODE where permissions are required.

For this exercise, select 4952942 as the SYS_LOC_CODE.

7.Choose the number of land_access_days where permission will be required and populate the other fields if the information is available.

For this exercise, set the land_access_days to 5.

spm-new-land-access

8.Select the Create button.

9.Select the OK button to complete the planned task.

10.SPM will take a few moments to create the samples and return a confirmation message. Select the OK button.

 

Warning Small

If Land Access information is added to the plan after a task is scheduled, the land access information will not be available for the scheduled task. The task must be unscheduled and rescheduled to be able to update the land access status.

 

 

Goal

Objective: Update Land Access for a Scheduled Task

Update scheduled task-level land access requirements to reflect the status of access availability for individual scheduled events.

 

1.Schedule the task as described in Define, Plan and Schedule Sampling Events.

For this exercise, schedule Task1.SWQM.M_<your initials>_0218_002.

2.Click Land Access Status spm-land-access-status-button in the Plan group on the Plan ribbon on the main EQuIS SPM window.

3.Select the date in the Status Date pane at the bottom of the window.

For this exercise, select 02/15/2018.

4.Click the Reload Data button. Note that the records displayed are those pertaining to scheduled tasks with start dates falling within the Land Access Days value of the inquiry date.

spm-land-access-status-update

5.Highlight the desired Land Access Status record, and then click Update spm-add-button to open the Land Access Status window.

For this exercise, highlight the Land Access Status record for 4952942.

6.Adjust the Status, Approved Start Date, Approved End Date, and other fields as desired.

For this exercise, set the Status to Accepted, the Approved Start Date to 02/12/2018 and the Approved End Date to 02/16/2018.

7.Click the Create button.

8.Click the OK button to save and close the Land Access Status window.

 

 

Goal

Objective: Generate Land Access Reports

The Land Access report calculates a date range and displays the information for locations with a land access requirement within the date range.

1.Select the Land Access spm-land-access-status-button report from the Reports ribbon on the main EQuIS SPM window.

2.Enter the desired report parameters on the SPM Land Access parameter window.

For this exrcise, select SJ River Monitoring_<your initials> as the Plan Code and Task1.SWQM.M_<your initials>_0218_002 as the SPM Task Code.

3.Select Go pro-report-go to run the report. A report opens in MS Excel showing the task summary, access summary and access detailed information.

spm-land-access-report